Mutapa Gold Profit Jumps 57% as US$240m Expansion Advances

HARARE – Zimbabwe’s state-owned Mutapa Gold Resources reported a 57 percent increase in quarterly after-tax profit to US$45 million, benefiting from higher gold prices and improved ore grades as the mining group accelerates a US$240 million expansion programme aimed at significantly increasing production.

The company, a subsidiary of the Mutapa Investment Fund, said revenue for the three months ended September 30 rose 39 percent to US$127 million, while gold production increased 14 percent to 30,116 ounces from 26,405 ounces a year earlier.

The average realised gold price climbed 22 percent to US$4,211 an ounce, helping earnings before interest, tax, depreciation and amortisation (EBITDA) increase 58 percent to US$67 million, representing a margin of approximately 53 percent.

The results, presented at a news conference in Harare on Wednesday, highlight the growing contribution of Zimbabwe’s gold industry to the earnings of state-controlled enterprises at a time when international bullion prices are providing substantial support to mining revenues.

More significantly, Mutapa achieved higher production despite processing less ore, suggesting that improvements in mining efficiency and mineral recovery are beginning to deliver measurable operational benefits.

Ore milled declined 6 percent to 713,000 tonnes after a planned 23-day shutdown of Mill Number 1 at Freda Rebecca Gold Mine in August.

However, average head grades improved to 1.50 grams per tonne from 1.32 grams, while recovery rates increased to 86 percent from 83 percent following the commissioning of additional leach tanks at Freda Rebecca and Jena Mines.

For mining investors, the combination of higher grades and improved recovery is particularly important because it allows producers to extract more saleable gold without necessarily increasing the volume of material processed.

The stronger operational performance was reflected in the company’s nine-month results, with revenue climbing 63 percent to US$402 million and after-tax profit tripling to US$156 million from US$52 million.

Mutapa Gold chief executive Patrick Shayawabaya said the company had already paid an interim dividend of US$35 million, with the board expected to consider a final distribution after the financial year ends.

The dividend represents a significant cash return from the state-owned mining portfolio, although the company’s expanding capital expenditure commitments will require careful management of future cash flows.

Despite the improved profitability, all-in sustaining costs increased 13 percent to US$2,337 an ounce, largely reflecting higher expenditure on maintaining mining operations. Cash operating costs remained unchanged at US$1,569 an ounce.

The company expects full-year gold production to exceed its previous forecast of 110,000 ounces, although financial performance is projected to remain broadly in line with expectations because higher output could be offset by weaker realised gold prices.

Attention is now turning to the Shamva Hill Project, where implementation began on October 1, with completion scheduled for December 2028.

The US$240 million development is expected to increase annual production from approximately 25,000 ounces to 80,000 ounces, substantially expanding the group’s production capacity.

Eleven Zimbabwean banks have committed to a syndicated financing facility that has increased to US$160 million from an initial US$110 million, with loan drawdowns already underway.

The participation of domestic banks demonstrates the growing role of local financial institutions in financing large-scale mining investment, although the project’s longer-term funding requirements remain dependent on securing additional external financing.

Mutapa expects the domestic facility to support development until around September 2027, while negotiations over the external loan component continue.

A separate expansion at Jena Mines, intended to raise annual production from 15,000 ounces to approximately 40,000 ounces, is expected to begin in the second quarter of 2027, subject to the completion of exploration and feasibility studies.

The company has also completed approximately 88,000 metres of diamond drilling against a planned 198,000 metres, with a resource upgrade at Freda Rebecca anticipated in January 2027.

However, the operational update raises a separate question about mine safety. While management reported one lost-time injury during the quarter, compared with two a year earlier, a table distributed to journalists recorded one fatality during the nine months to September.

The accompanying narrative did not explain the circumstances of the reported death.

For Zimbabwe’s mining sector, Mutapa Gold’s results illustrate the potential financial returns from combining favourable commodity prices with improvements in operational productivity.

The more demanding test will come as the company undertakes its expansion programme, when project execution, financing costs, safety performance and gold-price volatility will determine whether the current earnings momentum can be sustained.

With significant new investment planned and domestic banks increasing their exposure to mining projects, Mutapa Gold’s performance is becoming an important indicator of whether Zimbabwe’s state-owned mining assets can generate sustainable commercial returns while contributing to broader economic development.